The FLNG, which is part of the Coral South
Project, will be now towed and moored at its operating site in the Rovuma basin
offshore Mozambique. Production startup is expected in the second half of 2022,
and it will contribute to increase gas availability in a tight market.
Coral South Project achieved Final Investment
Decision in 2017, only 36 months after the last appraisal well. FLNG
fabrication and construction activities started in 2018 and were completed on
cost and on time, despite the pandemic. While performing the construction
activities in Korea, several significant activities were undertaken in
Mozambique, with full support from the Mozambican Authorities, including the
ultra-deep water (2000m wd) drilling and completion campaign that involved the
highest technological and operational skills and equipment.
The Coral South Project will generate
significant Government take for the Country while creating more than 800 new
jobs during the operation period.
Stefano Maione, Director Development,
Operations & Energy Efficiency at Eni, said: “The Coral Sul FLNG is a
world-class feat of engineering, construction know-how and technology, suited
to kick-off the development of Mozambique’s world-class resources. The project
fits integrally with and within the Eni’s energy transition strategy, as we
move towards a decarbonised energy future, in which gas is playing an essential
and transitional role”.
Coral-Sul FLNG has implemented an energy
optimization approach, integrated in the design via a systematic analysis of
energy efficiency improvements. These include among others, zero flaring during
normal operations, use of thermal efficient aero-derivative gas turbines for
refrigerant compressors and power generation, use of Dry Low NOx technology to
reduce NOx emission and waste heat recovery systems for gas processing.
The Coral Sul FLNG is 432 meters long and 66 meters wide, weighs around 220,000 tons and has the capacity to accommodate up to 350 people in its eight-story Living Quarter module. Once the FLNG facility will be in place, the installation campaign will begin, including mooring and hook-up operations at a water-depth of around 2,000 meters by means of 20 mooring lines that totally weight 9,000 tons. FLNG treatment and liquefaction installation has a gas liquefaction capacity of 3.4 million tons per year (MTPA) and will put in production 450 billion cubic meters of gas from the giant Coral reservoir, located in the offshore Rovuma Basin.
About Eni
Eni has been present in Mozambique since 2006.
Between 2011 and 2014, the company discovered supergiant natural gas resources
in the Rovuma basin, in the Coral, Mamba Complex and Agulha reservoirs, holding
estimated 2,400 billion cubic metres of gas in place. Eni also holds
exploration rights to offshore blocks A5-B, Z5-C and Z5-D in the
Angoche and Zambezi basins.
About Area 4
Area 4 is operated by Mozambique Rovuma
Venture S.p.A. (MRV), an incorporated joint venture owned by Eni, ExxonMobil
and CNPC, which holds a 70 percent interest in the Area 4 exploration and
production concession contract. In addition to MRV, Galp, KOGAS and Empresa
Nacional de Hidrocarbonetos E.P. each hold a 10 percent interest in Area 4. Eni
is the offshore Delegated Operator and is leading the construction and
operation of the floating liquefied natural gas facility on behalf of MRV.