The spillway repair works on the Massingir dam, a project budgeted at
US$60 million, are due to begin next May, said Edgar Chongo, the
technician assigned to the Limpopo Basin Management Unit.The contract, awarded to a consortium involving Italian company
Cooperativa Muratori and Cementisti (CMC) di Ravenna and South Africa’s
WBHO, will take 24 months and its financing is secured with funds from
the Mozambique State Budget and the African Development Bank.The project, according to Chongo, essentially aims to ensure the
efficient operation of the dam, through large water discharges, whilst
taking into account water needs downstream.Chongo also told Mozambican daily newspaper Notícias, that once work was
complete conditions would be in place for the viability of the
Massingir Agro-Industrial (MAI) project, for irrigation of an area of
37 thousand hectares and production of cane sugar in Massingir
district.The President of Mozambique recently opened an auxiliary spillway at the
dam at a cost of just over US$34 million, which will double previous
water flow capacity in the event of floods, to 20,000 cubic metres per
second.The Massingir dam, built in the early 1970s, was designed to irrigate an
area of about 90 thousand hectares along the Limpopo River valley and
to control flooding. Macauhub in its March 27, 2013, edition reported that "work to repair
the Massingir dam, in Mozambique’s Gaza province, is expected to cost
more than double initial estimates, and will now cost an estimated US$30
million, said Suzana Loforte, the national director for Water."The initial valuation would have been according to this March 2013
article around "US$13 million to replace the infrastructure damaged in
May 2008."