The Maputo Port Development
Company (MPDC) has announced today that Mota-Engil will carry out 51.7 million
Euros’-worth of work, rehabilitating one kilometre of mooring berths from June
onwards.Once rehabilitated, the quays will be able to receive larger ships, as
provided for in the port development masterplan, the company says in a
statement.The rehabilitation follows the dredging of the port access channel in
January 2017, at a cost of EUR 70 million.Combined, the works, scheduled from
June until the end of next year, pave the way for a 40 percent increase in the
cargo capacity in Maputo and 55 percent of the cargo capacity in Matola.In
2017, MPDC registered a 22 percent increase in volumes handled in Maputo, with
18.2 million tons of cargo against 14.9 million in the previous year. The port
expects to handle around 22 million tons of cargo this year.Friday, March 16, 2018
EUR 51.7M works in Port of Maputo
The Maputo Port Development
Company (MPDC) has announced today that Mota-Engil will carry out 51.7 million
Euros’-worth of work, rehabilitating one kilometre of mooring berths from June
onwards.Once rehabilitated, the quays will be able to receive larger ships, as
provided for in the port development masterplan, the company says in a
statement.The rehabilitation follows the dredging of the port access channel in
January 2017, at a cost of EUR 70 million.Combined, the works, scheduled from
June until the end of next year, pave the way for a 40 percent increase in the
cargo capacity in Maputo and 55 percent of the cargo capacity in Matola.In
2017, MPDC registered a 22 percent increase in volumes handled in Maputo, with
18.2 million tons of cargo against 14.9 million in the previous year. The port
expects to handle around 22 million tons of cargo this year.Hydroelectric plant is to invest EUR 40 million
The
Cahora Bassa Hydroelectric Plant will invest EUR 40 million modernising a
substation in order to improve the quality of energy exported to South Africa,
the company says in a statement.The substation is located in Songo, next to the
Cahora Bassa dam, and is the cause of a sharp degradation in the
conversion of alternating into direct current for export to South Africa, the
HCB explains.
The
Brownfield Project has been assigned the task of modernising the substation,
the second phase of which is the subject of today’s announcement.
“With
the Brownfield Project, HCB essentially aims to minimise the risk of reducing
the availability and reliability of the energy conversion system,” the company
adds.
Among
other things, the acquisition of a new 400kV converter transformer, the
rehabilitation of 15 other converting transformers and the import and
installation of an emergency generator are currently underway.HCB has also
launched a public tender for the third phase of the work, which will run from
2018 to 2026.The modernisation of Cahora Bassa is part of an overall plan called
Capex Vital, budgeted at EUR 500 million. This is “a strategic planning tool
with a ten-year horizon that aims to optimise the production and transportation
of energy”, HCB explains.